Leask Marine complete major marine & diving project for NKT HVC at Moray East Offshore Wind Farm
Published on January 27 2021
The Leask Marine team recently completed a six-month campaign of works on behalf of NKT at the Moray East Offshore Wind Farm. The project used a number of Leask Marine resources with the supply of the C-Fenna, C-Spartan, line-boats, and full diving spread including chamber and LARS, and airlift dredging.
The scope of works included the nearshore airlift dredging for laying 3no. HDD pipes, preparing the Bellmouths for the cable pull-ins, pull though the messenger wires, and post pull in works including kennel installations and dive surveys.